From 2012 A Spring |
Tuesday, July 31, 2012
Removing 127 Ewingville.
A contact with Ben Worley, Project Manager for the city, states that the contractor plans to start this week removing the house at 127 Ewingville.
Thursday, July 26, 2012
Dam Cam
Listening to WAKM from New Hampshire on 7/25/2012 I learned that the dam on the Harpeth has been removed. This is the Dam Cam.
There is now talk about a Greenway along the river. We will want to be aware now and proactive about the placement of the greenway. Please send any contact information to me at MarsCreate@aol.com
There is now talk about a Greenway along the river. We will want to be aware now and proactive about the placement of the greenway. Please send any contact information to me at MarsCreate@aol.com
Monday, July 16, 2012
Delayed Start
We have had a communication from Ben Worley, Project Manager with the City of Franklin. He states that the contractor got behind and could not start the demolition July 11 or 12. As of July 16, 2012, the contractor is moving in. He will be on the street until houses at 115, 117 and 127 Ewingville are gone.
Mr. Worley has asked that all questions be asked to him and not to the contractor and workers. Contact information to the right of this posting.
Mr. Worley has asked that all questions be asked to him and not to the contractor and workers. Contact information to the right of this posting.
Tuesday, July 3, 2012
Demolition to begin
The
contractor, Modern Day Wrecking Company, Nashville, is completing paperwork to
begin the removal of properties at 117 and 119 Ewingville. The contractor
is planning to start next Wednesday or Thursday, July 11 or July 12, 2012.
Ben Worley, project manager states
that any information gotten from workers onsite should not be
taken to be the truth. If there is a question that comes up please ask him.
Ben Worley
ROW Agent / Project Manager
Engineering Department
615-791-3218
Modern Day Wrecking Company is permitted to work
7-6 M-F and 9-6 on Sa.
Subscribe to:
Posts (Atom)